Agile Lifecycles for Geographically Distributed Teams, Part 2 - No Fluff Just Stuff

Agile Lifecycles for Geographically Distributed Teams, Part 2

Posted by: Johanna Rothman on January 25, 2012

Example 2: Using a Project Manager with Kanban, Silo’d Teams

This is a product development organization with developers in Italy, testers in India, more developers in New York, product owners and project managers in California.

This organization first tried iterations, but the team could never get to done. The problem was that the stories were too large. Normally I suggest smaller iterations, but one of the developers suggested they move to kanban.

The New York developers had a problem biting off more than they could chew. So nothing moved across their board. The Italy developers had a board where the work did move across the board. The teams took pictures of their boards every day and shared the work across a project-based wiki. That allowed the New York-based developers to see the work move across the Italy board. And, that encouraged the New Yorkers to call the Italians and ask some questions. That helped the New Yorkers to change the size of their work by working with the product owners.

Now, why did the New Yorkers have such trouble originally? Because the developers “knew better” than the product owners, so they changed the stories into architectural features when they had originally received them. (Now they don’t. They leave the stories as real stories.)

Release planning: Management in California plan with agile roadmaps. They have features planned specifically week-by-week for the next 6 weeks, and have more of a quarter-by-quarter approach after that.

Iteration planning: No iteration planning because they are using kanban.

Daily commitment: No daily commitment needed because they use kanban. They do have a checkin a few times a week with each other as a technical team to make sure they don’t create bottlenecks and that they respect the WIP (work in progress) limits.

At one point, both the New York and Italy developer teams created automated tests so that the testers could catch up and stay caught up with regression tests. They add a story like that every couple of weeks, and they are paying down their automated testing debt.

The Project manager keeps an eye on the WIP, work in progress. Project manager also shepherds the product owner into keeping the queue of incoming work full and properly ranked. The product owner is notorious for changing the incoming work queue all the time. Project manager makes sure the team does retrospectives and is a little unclear how to do them in such a distributed team. The project manager is not so sure their retrospectives are working, and has started an obstacle list, to make sure the team has transparency for their obstacles.

Measurements: cumulative flow, average time to release a feature into the product.

(Want to learn to work more effectively on your geographically distributed team? Join Shane Hastie and me in a workshop April 17-18, 2012.)

Johanna Rothman

About Johanna Rothman

Johanna Rothman, known as the “Pragmatic Manager,” offers frank advice for your tough problems. She helps leaders and teams learn to see simple and reasonable things that might work. Equipped with that knowledge, they can decide how to adapt their product development.

With her trademark practicality and humor, Johanna is the author of 18 books about many aspects of product development. She’s written these books:

  • Project Lifecycles: How to Reduce Risks, Release Successful Products, and Increase Agility
  • Become a Successful Independent Consultant
  • Free Your Inner Nonfiction Writer
  • Modern Management Made Easy series: Practical Ways to Manage Yourself; Practical Ways to Lead and Serve (Manage) Others; Practical Ways to Lead an Innovative Organization
  • Write a Conference Proposal the Conference Wants and Accepts
  • From Chaos to Successful Distributed Agile Teams (with Mark Kilby)
  • Create Your Successful Agile Project: Collaborate, Measure, Estimate, Deliver
  • Agile and Lean Program Management: Scaling Collaboration Across the Organization
  • Manage Your Project Portfolio: Increase Your Capacity and Finish More Projects, 2nd edition
  • Project Portfolio Tips: Twelve Ideas for Focusing on the Work You Need to Start & Finish
  • Diving for Hidden Treasures: Finding the Value in Your Project Portfolio (with Jutta Eckstein)
  • Predicting the Unpredictable: Pragmatic Approaches to Estimating Project Schedule or Cost
  • Manage Your Job Search
  • Hiring Geeks That Fit
  • The 2008 Jolt Productivity award-winning Manage It! Your Guide to Modern, Pragmatic Project Management
  • Behind Closed Doors: Secrets of Great Management (with Esther Derby)

In addition to articles and columns on various sites, Johanna writes the Managing Product Development blog on her website, jrothman.com, as well as a personal blog on createadaptablelife.com.

Why Attend the NFJS Tour?

  • » Cutting-Edge Technologies
  • » Agile Practices
  • » Peer Exchange

Current Topics:

  • Languages on the JVM: Scala, Groovy, Clojure
  • Enterprise Java
  • Core Java, Java 8
  • Agility
  • Testing: Geb, Spock, Easyb
  • REST
  • NoSQL: MongoDB, Cassandra
  • Hadoop
  • Spring 4
  • Cloud
  • Automation Tools: Gradle, Git, Jenkins, Sonar
  • HTML5, CSS3, AngularJS, jQuery, Usability
  • Mobile Apps - iPhone and Android
  • More...
Learn More »